Sector E-12 Possession: CDA Says 68% of Work Is Done

Sector E-12 possession: CDA says 68% of development is done as plots are handed over

Sector E-12 possession is moving ahead: the Capital Development Authority (CDA) said on 20 November 2026 that more than 68% of the development work in the Islamabad sector is complete. Where work is finished, CDA is handing over plots to allottees so they can build houses.

E-12 has waited about four decades for development. CDA also says it has received many applications from allottees who want possession of their plots.

Where Sector E-12 possession and development stand

CDA’s update gives this progress, sub-sector by sub-sector:

  • E-12/1: TST work is complete in 25 streets, and earthwork is done in the remaining streets.
  • E-12/2: TST work is complete in 31 streets. In the other streets, TST will start once earth and base work are finished.
  • E-12/3: TST work is complete in 15 streets, while earthwork and base work continue in the rest.
  • E-12/4: earthwork is complete. Base, sub-base, drainage and sewerage work is under way.

Asphalt work is in progress on Service Road Khayaban-e-Iqbal and on Margalla Road next to the sector. On Service Road East, earthwork, base, sub-base and drainage are complete. Underground work for the electricity supply is also going on.

CDA says it took back about 1,135 kanals of land from illegal occupation to clear the way. The CDA chairman, Sohail Ashraf, told the departments to remove the remaining obstacles and finish the work on a priority basis.

What it means for buyers and allottees in E-12

First, possession is not yet sector-wide. CDA hands over plots where development is complete, so the street and sub-sector matter. E-12/1 and E-12/2 have the most finished streets, while E-12/4 is at an earlier stage.

Second, if you hold an E-12 plot, you can apply to CDA for possession and then start building. Before you buy a plot, ask the seller which sub-sector and street it is in, and check its possession status with CDA.

Third, CDA has also charged development charges to E-12 allottees under a CDA Board decision of 12 July 2024. Check that these are settled before a transfer.

For the sector’s location, plot sizes and access, see our Sector E-12 Islamabad guide.

Sources and updates

CDA, “Work on Sector Development proceeding at a fast pace in Sector E-12, after remained Pending for Four Decades”, press release, 20 November 2026 (cda.gov.pk). CDA public notice to Sector E-12 plot owners on development charges (CDA Board decision of 12 July 2024), 28 November 2024 (cda.gov.pk public notices). Also reported by ProPakistani, 20 November 2026. Post published 24 November 2026.